Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.184 | 1.184 | 0.300 | 0.884 | 0.890 | 0.000 |
4W654 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No.- 49618 Date 29-3-2023
TS Amount (lakhs) : 100.27 Lacs
Financial Detail
Sanction Cost : 100.27 Lacs
Resanction Cost : 100.27 Lacs
Exp. Upto Last Fy : 19.86 Lacs
For CFY 2024-2025
Remaining : 80.41 Lacs
Demand : 50.00 Lacs
Allotment : 15.00 Lacs
Exp in CFY : 11.61 Lacs
Total Up to Date Exp : 31.48 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 1 month ago
29 Mar 2023
Tentative Completion date:
4 months 3 weeks from now
16 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 17.10.2023 एवं कार्य पूर्ण करने की तिथि 16.10.2024 है।
दीवार एवं नाली का कार्य पूर्ण। 300 मीटर में टाॅप व टाईल्स का कार्य पूर्ण। शेष टाईल्स का कार्य प्रगति पर है।
-- as on 10-Apr-2024
Physical Peramenters