Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 3.500 | 0.000 |
4W657 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई फाईल सं.50206 दिनांक 04.05.2023
TS Amount (lakhs) : 204.39 Lacs
Financial Detail
Sanction Cost : 204.39 Lacs
Resanction Cost : 204.39 Lacs
Exp. Upto Last Fy : 33.99 Lacs
For CFY 2024-2025
Remaining : 170.40 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 33.99 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
1 year 2 weeks ago
04 May 2023
Tentative Completion date:
6 months 3 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 16.12.2023 एवं कार्य समाप्ति की तिथि 15.12.2024 है। 2किमी. में सोलिंग का कार्य पूर्ण। 2 किमी. में पार्ट-2 का कार्य पूर्ण। शेष दीवार, स्पकर एवं सोलिंग का कार्य प्रगति पर है। -- as on 10-Apr-2024
Physical Peramenters