Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 0.000 | 0.000 |
4W658 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : प्रमुख अभियन्ता एवं विभागाध्यक्ष, लो0नि0वि0, देहरादून के पत्रांक 895/07याता.-पी.एम.जी.एस.वाई.-नि.111 दिनांक 16.5.2023
TS Amount (lakhs) : 82.56 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
82.56
Resanction Cost :
82.56
Tentative Cost :
82.56
Exp. Upto Last Fy : 69.36
For CFY 2024-2025
Remaining : 13.20
Demand : 13.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 69.36
Work completed
Physical Progress:
At start of FY 2024-2025 : 90 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
16 May 2023
Tentative Completion date:
3 months 3 weeks ago
21 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 26-Jun-2024
Physical Peramenters