Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 0.000 | 4.5 | 2.500 | 0.000 |
4W691 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई-फाईल सं. 39751 दिनांक 07.08.2023
TS Amount (lakhs) : 222.02 Lacs
Financial Detail
Sanction Cost : 222.07 Lacs
Resanction Cost : 222.07 Lacs
Exp. Upto Last Fy : 38.62 Lacs
For CFY 2024-2025
Remaining : 183.45 Lacs
Demand : 100.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 38.62 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
6 months 3 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध के अनुसार कार्य प्रारम्भ की तिथि 16.12.2023 एवं कार्य समाप्ति की तिथि 15.12.2024 है।
4 किमी. में पार्ट-2 का कार्य पूर्ण। 1 किमी. में सोलिंग का कार्य पूर्ण। शेष कार्य प्रगति पर हेै।
-- as on 10-Apr-2024
Physical Peramenters