Work Profile Report [51W1047]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 - 793/।।।(2)/14-28 प्रा0आ0/2013 टी0सी0 दिनांक 08.02.2014
TS Amount (lakhs) : 210.29 Lacs
Budget Financial Head : NABARD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
210.29
Resanction Cost :
210.29
Tentative Cost :
210.29
Exp. Upto Last Fy :
139.76
For CFY 2025-2026
Remaining :
70.53
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
139.76
In Maintenance After Completion
Sanction on : 11 years 10 months ago
08 Feb 2014
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 years 9 months ago
31 Mar 2022
Actual Completion Date : 4 years 1 month ago
30 Nov 2021
Physical Linear Components
Remark
Overall Saving 70.53 has been recorded as expected cost of work reduced from 210.29 to 139.76 . -- as on 29-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand