Work Profile Report [51W1083]

निक्षेप मद के अन्तर्गत देहरादून - रायपुर मोटर मार्ग में सर्वेचैक से चूना भट्टा पुल तक डेªनेज का कार्य।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : DSCL Letter No 5268/DSCL/20-21

TS Amount (lakhs) : 489.4 Lacs

Budget Financial Head : SRMD ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

479.40

Resanction Cost :

479.40

Tentative Cost :

479.40

Exp. Upto Last Fy :

329.01

For CFY 2024-2025

Remaining :

150.39

Demand :

12.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

329.01

Work completed

Sanction on : 3 years 10 months ago

30 Dec 2020

Physical Progress:

At start of FY 2024-2025 :

50 %

Up to Date :

100 %

Tentative Completion date on : 7 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Jobs
1
1
1
-

Remark

view all

work completed -- as on 19-Oct-2024

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: