Work Profile Report [51W1115]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 491/(I) III(2) (MLA)/2017
TS Amount (lakhs) : 109.11 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
109.11
Resanction Cost :
109.11
Tentative Cost :
109.11
Exp. Upto Last Fy :
96.65
For CFY 2024-2025
Remaining :
12.46
Demand :
3.01
Allotment :
5.71
Exp in CFY :
3.01
Total Up to Date Exp :
99.66
Work completed
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date : 1 year 8 months ago
31 Mar 2023
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: