Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.116 | 1.116 | 1.116 | 0 | 0.000 | 0.000 |
51W1115 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 491/(I) III(2) (MLA)/2017
TS Amount (lakhs) : 109.11 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
109.11
Resanction Cost :
109.11
Tentative Cost :
109.11
Exp. Upto Last Fy : 96.65
For CFY 2024-2025
Remaining : 12.46
Demand : 12.45
Allotment : 0.00
Exp in CFY : 0.30
Total Up to Date Exp : 96.95
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Physical Peramenters