Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.3 | 2.2 | 2.200 | 0 | 0.000 | 0.000 |
51W1158 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : मसूरी देहरादून विकास प्राधिकरण का पत्र संख्या 2371/22-23 दिनांक 04.01.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
677.08
Resanction Cost :
677.08
Tentative Cost :
677.08
Exp. Upto Last Fy : 599.70
For CFY 2024-2025
Remaining : 77.38
Demand : 77.40
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 599.70
Work completed
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 100 %
Sanction on :
1 year 6 months ago
04 Jan 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व का भुगतान अवशेष। पुनरीक्षित आगणन रू0 1058.78 लाख का गठित कर मुख्य अभियन्ता कार्यालय के पत्रांक 5104/09 (213) याता स्तर-1 /2013 दिनांक 16.08.23 के द्वारा धनावंटन हेतु सचिव, एम.डी.डी.ए. देहरादून को प्रेषित। -- as on 04-Jan-2024