Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7.25 | 7.25 | 7.250 | 0 | 0.000 | 0.000 |
51W1163 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter no 26103 Dt. 15.12.2022
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
136.49
Resanction Cost :
136.49
Tentative Cost :
136.49
Exp. Upto Last Fy : 117.26
For CFY 2024-2025
Remaining : 19.23
Demand : 19.23
Allotment : 0.00
Exp in CFY : 19.18
Total Up to Date Exp : 136.44
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 7 months ago
15 Dec 2022
Tentative Completion date:
3 months 2 weeks ago
30 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Physical Peramenters