Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.03 | 2.03 | 2.030 | 0 | 0.000 | 0.000 |
51W1167 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E lettre No 26119 Dtt. 31.3.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
157.00
Resanction Cost :
157.00
Tentative Cost :
157.00
Exp. Upto Last Fy : 142.40
For CFY 2024-2025
Remaining : 14.60
Demand : 14.60
Allotment : 11.12
Exp in CFY : 11.12
Total Up to Date Exp : 153.52
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 3 months ago
31 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
30 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024