Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.24 | 3.24 | 0.000 | 3.24 | 3.240 | 3.140 |
51W1169 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 37290 Dt. 29.3.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
312.61
Resanction Cost :
312.61
Tentative Cost :
312.61
Exp. Upto Last Fy : 198.99
For CFY 2024-2025
Remaining : 113.62
Demand : 113.61
Allotment : 113.00
Exp in CFY : 79.62
Total Up to Date Exp : 278.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 90 %
Sanction on :
1 year 3 months ago
29 Mar 2023
Tentative Completion date:
3 weeks 5 days from now
13 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 30-Apr-2024
Physical Peramenters