Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
51W1173 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 15556 Dt. 31.3.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 332.79 Lacs
Resanction Cost : 332.79 Lacs
Exp. Upto Last Fy : 129.41 Lacs
For CFY 2024-2025
Remaining : 203.38 Lacs
Demand : 203.38 Lacs
Allotment : 203.38 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 129.41 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 50 %
Sanction on :
1 year 1 month ago
31 Mar 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 08-Nov-2023