Work Profile Report [51W1174]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : ENC letter No 5455/79 Budget (SDMF)/2022-23 Dt. 29.3.23
TS Amount (lakhs) : 225.25 Lacs
Budget Financial Head : Deposit ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
225.25
Resanction Cost :
225.25
Tentative Cost :
225.25
Exp. Upto Last Fy :
90.00
For CFY 2025-2026
Remaining :
135.25
Demand :
135.25
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
90.00
Work completed
Sanction on : 2 years 8 months ago
29 Mar 2023
Physical Progress:
At start of FY 2025-2026 :
60 %
Up to Date :
100 %
Tentative Completion date on : 1 year 4 months ago
31 Jul 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 03-Nov-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: