Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
No of Bridges | 1 | 1 | 0 | 1 | 0 | 0 |
Span of Bridges [m] | 60 | 60 | 0.000 | 60 | 0.000 | 0.000 |
51W1182 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 49511 Dt. 15.03.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
12.00
Resanction Cost :
12.00
Tentative Cost :
12.00
Exp. Upto Last Fy : 3.00
For CFY 2024-2025
Remaining : 9.00
Demand : 9.00
Allotment : 0.00
Exp in CFY : 0.04
Total Up to Date Exp : 3.04
Unstarted Work
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
1 year 4 months ago
15 Mar 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डिजाइन , डी.पी.आर व भूमि अधिग्रहण की कार्यवाही गतिमान है -- as on 15-Jul-2024
Physical Peramenters