Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.55 | 0.55 | 0.55 | 0 |
51W1187 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter no 34340 Dt. 27 June 2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 60.83 Lacs
Resanction Cost : 60.83 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 60.73 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 months 3 weeks ago
27 Jun 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रारम्भ। कार्य वन विभाग द्वारा भूमि विवाद के कारण लम्बित है। -- as on 04-Jan-2024
Physical Peramenters