Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 0.000 | 1.6 | 1.600 | 1.600 |
51W1189 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 47588 Dt. 28.6.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.63
Resanction Cost :
96.63
Tentative Cost :
96.23
Saving
0.40
Exp. Upto Last Fy : 27.21
For CFY 2024-2025
Remaining : 69.42
Demand : 69.42
Allotment : 0.00
Exp in CFY : 59.13
Total Up to Date Exp : 86.34
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 2 weeks ago
28 Jun 2023
Tentative Completion date:
3 months 1 day ago
16 Apr 2024
Actual Completion Date:
3 months 1 day ago
16 Apr 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 26-Jun-2024
Physical Peramenters