Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.6 | 1.6 | 0.000 | 1.6 | 1.600 | 0.000 |
51W1189 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 47588 Dt. 28.6.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 96.63 Lacs
Resanction Cost : 96.63 Lacs
Exp. Upto Last Fy : 27.21 Lacs
For CFY 2024-2025
Remaining : 69.42 Lacs
Demand : 69.42 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 27.21 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
10 months 3 weeks ago
28 Jun 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 27-Jan-2024
Physical Peramenters