Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.000 | 1.15 | 1.150 | 0.000 |
51W1193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E File No 49511 Dt. 4.08.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 364.72 Lacs
Resanction Cost : 364.72 Lacs
Exp. Upto Last Fy : 139.64 Lacs
For CFY 2024-2025
Remaining : 225.08 Lacs
Demand : 225.08 Lacs
Allotment : 100.60 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 139.64 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 45 %
Up to Date : 45 %
Sanction on :
9 months 2 weeks ago
04 Aug 2023
Tentative Completion date:
2 months 3 weeks from now
15 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 08-Nov-2023
Physical Peramenters