Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 |
51W1195 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Letter No 1830/79 Budget ( SDMF) /2023-24 Dt. 31.07.2023
TS Amount (lakhs) : 275.37 Lacs
Financial Detail
Sanction Cost : 275.37 Lacs
Resanction Cost : 275.37 Lacs
Exp. Upto Last Fy : 75.06 Lacs
For CFY 2024-2025
Remaining : 200.31 Lacs
Demand : 200.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 75.06 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
9 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
2 weeks 3 days ago
02 May 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 04-Apr-2024
Physical Peramenters