Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 1 | 0 | 0 | 0 |
51W1197 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ENC Letter No 1830/79 Budget ( SDMF) /2023-24 Dt. 31.07.2023
TS Amount (lakhs) : 33.13 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
33.13
Resanction Cost :
33.13
Tentative Cost :
33.13
Exp. Upto Last Fy : 16.66
For CFY 2024-2025
Remaining : 16.47
Demand : 16.47
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 16.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 25-Apr-2024
Physical Peramenters