Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 33 | 33 | 33.000 | 0 | 0.000 | 0.000 |
51W1201 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2937/।।।(2)/23-01 (प्रा0आ0)/2019 दिनांक 11 अगस्त 2023
TS Amount (lakhs) : 64.77 Lacs
Financial Detail
Sanction Cost : 64.77 Lacs
Resanction Cost : 64.77 Lacs
Exp. Upto Last Fy : 64.72 Lacs
For CFY 2024-2025
Remaining : 0.05 Lacs
Demand : 0.05 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 64.72 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 months 1 week ago
11 Aug 2023
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 08-Apr-2024
Physical Peramenters