Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 32.6 | 32.6 | 32.600 | 0 | 0.000 | 0.000 |
51W1202 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 'kk0la0 2937/AAA¼2½/23&01 ¼çk0vk0½/2019 fnukad 11 vxLr 2023
TS Amount (lakhs) : 83.28 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
83.28
Resanction Cost :
83.28
Tentative Cost :
83.28
Exp. Upto Last Fy : 75.68
For CFY 2024-2025
Remaining : 7.60
Demand : 7.60
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 75.68
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 years 5 months ago
12 Feb 2017
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
3 months 3 weeks ago
20 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 08-Apr-2024