Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 1.200 | 0 | 0.000 | 0.000 |
51W1207 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 60170 Dt. 22.09.2023
TS Amount (lakhs) : 49.35 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.35
Resanction Cost :
49.35
Tentative Cost :
49.35
Exp. Upto Last Fy : 44.59
For CFY 2024-2025
Remaining : 4.76
Demand : 4.76
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 44.59
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 months 3 weeks ago
22 Sep 2023
Tentative Completion date:
8 months 2 days ago
15 Nov 2023
Actual Completion Date:
8 months 2 days ago
15 Nov 2023
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Physical Peramenters