Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.997 | 2.997 | 0.000 | 2.997 | 2.997 | 2.000 |
51W1208 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter No - 37290 Section -2 Dt. 12.05.2023
TS Amount (lakhs) : 143.07 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
143.07
Resanction Cost :
143.07
Tentative Cost :
143.07
Exp. Upto Last Fy : 15.37
For CFY 2024-2025
Remaining : 127.70
Demand : 127.70
Allotment : 127.70
Exp in CFY : 60.48
Total Up to Date Exp : 75.85
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 65 %
Sanction on :
1 year 2 months ago
12 May 2023
Tentative Completion date:
1 day 5 hours ago
16 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 02-Mar-2024
Physical Peramenters