Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.4 | 2.4 | 2.400 | 0 | 0.000 | 0.000 |
51W1209 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter No 60170 Dt. 06.10.2023
TS Amount (lakhs) : 144.78 Lacs
Financial Detail
Sanction Cost : 144.78 Lacs
Resanction Cost : 144.78 Lacs
Exp. Upto Last Fy : 88.97 Lacs
For CFY 2024-2025
Remaining : 55.81 Lacs
Demand : 55.81 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 88.97 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
7 months 1 week ago
06 Oct 2023
Tentative Completion date:
6 months 3 days ago
15 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष । -- as on 30-Apr-2024
Physical Peramenters