Work Profile Report [51W1216]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 26119 Dt. 11.10.2023
TS Amount (lakhs) : 234.66 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
234.66
Resanction Cost :
234.66
Tentative Cost :
234.66
Exp. Upto Last Fy :
89.53
For CFY 2024-2025
Remaining :
145.13
Demand :
133.84
Allotment :
98.60
Exp in CFY :
98.60
Total Up to Date Exp :
188.13
Construction Started
Sanction on : 1 year 2 months ago
11 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on : 4 weeks 1 day ago
25 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: