Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.79 | 3.79 | 3.79 | 0 |
51W1216 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 26119 Dt. 11.10.2023
TS Amount (lakhs) : 234.66 Lacs
Financial Detail
Sanction Cost : 234.66 Lacs
Resanction Cost : 234.66 Lacs
Exp. Upto Last Fy : 89.53 Lacs
For CFY 2024-2025
Remaining : 145.13 Lacs
Demand : 145.13 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 89.53 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
7 months 1 week ago
11 Oct 2023
Tentative Completion date:
1 month 5 days from now
25 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Mar-2024
Physical Peramenters