Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.79 | 3.79 | 0.000 | 3.79 | 3.790 | 2.600 |
51W1216 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 26119 Dt. 11.10.2023
TS Amount (lakhs) : 234.66 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
234.66
Resanction Cost :
234.66
Tentative Cost :
234.66
Exp. Upto Last Fy : 89.53
For CFY 2024-2025
Remaining : 145.13
Demand : 145.13
Allotment : 0.00
Exp in CFY : 44.70
Total Up to Date Exp : 134.23
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 60 %
Sanction on :
9 months 6 days ago
11 Oct 2023
Tentative Completion date:
4 months 1 week from now
25 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Mar-2024
Physical Peramenters