Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5.71 | 5.71 | 5.710 | 0 | 0.000 | 0.000 |
51W1220 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E Letter No 60170 Dt. 19.10.2023
TS Amount (lakhs) : 276.3 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
276.30
Resanction Cost :
276.30
Tentative Cost :
276.30
Exp. Upto Last Fy : 273.50
For CFY 2024-2025
Remaining : 2.80
Demand : 2.80
Allotment : 0.00
Exp in CFY : 0.11
Total Up to Date Exp : 273.62
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 months 4 weeks ago
19 Oct 2023
Tentative Completion date:
6 months 2 weeks ago
30 Dec 2023
Actual Completion Date:
6 months 2 weeks ago
30 Dec 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 08-Apr-2024
Physical Peramenters