Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.028 | 2.028 | 0.000 | 2.028 | 2.028 | 0.000 |
51W1241 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file no. 40094
TS Amount (lakhs) : 315.5 Lacs
Financial Detail
Sanction Cost : 319.50 Lacs
Resanction Cost : 319.50 Lacs
Exp. Upto Last Fy : 1.05 Lacs
For CFY 2024-2025
Remaining : 318.45 Lacs
Demand : 300.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 1.05 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 2 weeks ago
30 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Mar-2024
Physical Peramenters