Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 6.000 | 0.000 |
51W1244 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5082/III(2)/23-01 (TS)/2023 Dt. 09.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 153.64 Lacs
Resanction Cost : 153.64 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 153.64 Lacs
Demand : 153.64 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 1 week ago
09 Nov 2023
Tentative Completion date:
1 month 1 week from now
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबंध गठन की कार्यवाही की जा रही है -- as on 08-Apr-2024
Physical Peramenters