Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12.4 | 12.4 | 12.400 | 0 | 0.000 | 0.000 |
51W1245 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5082/III(2)/23-01 (TS)/2023 Dt. 09.11.2023
TS Amount (lakhs) : 7.76 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7.76
Resanction Cost :
7.76
Tentative Cost :
7.76
Exp. Upto Last Fy : 7.72
For CFY 2024-2025
Remaining : 0.04
Demand : 0.04
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 7.72
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 months 1 week ago
09 Nov 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
3 months 3 weeks ago
20 Mar 2024
Remark
Bottelneck: no issue
Work completed -- as on 01-Mar-2024
Physical Peramenters