Work Profile Report [51W1246]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 26103 Dt. 18 May 2023
TS Amount (lakhs) : 89.98 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
89.98
Resanction Cost :
89.98
Tentative Cost :
89.98
Exp. Upto Last Fy :
86.37
For CFY 2024-2025
Remaining :
3.61
Demand :
3.61
Allotment :
3.61
Exp in CFY :
5.16
Total Up to Date Exp :
91.53
Work completed
Sanction on : 1 year 7 months ago
18 May 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
30 Mar 2024
Actual Completion Date : 8 months 3 weeks ago
30 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 04-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: