Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.147 | 1.147 | 1.147 | 0 | 0.000 | 0.000 |
51W1246 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 26103 Dt. 18 May 2023
TS Amount (lakhs) : 89.98 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
89.98
Resanction Cost :
89.98
Tentative Cost :
89.98
Exp. Upto Last Fy : 86.37
For CFY 2024-2025
Remaining : 3.61
Demand : 3.61
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 86.37
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
1 year 1 month ago
18 May 2023
Tentative Completion date:
3 months 2 weeks ago
30 Mar 2024
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 04-Apr-2024
Physical Peramenters