Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.4 | 1.4 | 1.400 | 0 | 0.000 | 0.000 |
51W1251 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नगर निगम का पत्र संख्या 431/NCAP/Paving of Road /2023-24 Dt. 7.08.2023
TS Amount (lakhs) : 42.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.06
Resanction Cost :
42.06
Tentative Cost :
42.06
Exp. Upto Last Fy : 25.01
For CFY 2024-2025
Remaining : 17.05
Demand : 17.05
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 25.01
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
07 Aug 2023
Tentative Completion date:
5 months 4 weeks ago
19 Jan 2024
Actual Completion Date:
5 months 4 weeks ago
19 Jan 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 04-Apr-2024
Physical Peramenters