Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 0 | 0.000 | 0 | 2.000 | 0.000 |
51W1256 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : नगर निगम का पत्र संख्या 463/NCAP/Paving of Road /2023-24 Dt. 10.08.2023
TS Amount (lakhs) : 95.84 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
95.84
Resanction Cost :
95.84
Tentative Cost :
95.84
Exp. Upto Last Fy : 34.70
For CFY 2024-2025
Remaining : 61.14
Demand : 61.14
Allotment : 0.00
Exp in CFY : 21.82
Total Up to Date Exp : 56.53
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
1 month 2 weeks ago
31 May 2024
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष। -- as on 28-Jun-2024
Physical Peramenters