Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.025 | 2.025 | 0.000 | 2.025 | 2.025 | 0.000 |
51W1259 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 47588 Dt. 31.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
156.73
Resanction Cost :
156.73
Tentative Cost :
156.73
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 156.63
Demand : 156.63
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
7 months 3 weeks from now
13 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 08-Apr-2024
Physical Peramenters