Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.07 | 1.07 | 0.000 | 1.07 | 1.070 | 0.450 |
51W1260 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E letter No 56976 Dt.13.12.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.33
Resanction Cost :
30.33
Tentative Cost :
30.33
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 30.23
Demand : 30.23
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 42 %
Sanction on :
7 months 4 days ago
13 Dec 2023
Tentative Completion date:
2 months 4 weeks from now
17 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 04-Apr-2024
Physical Peramenters