Work Profile Report [51W1262]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter No 40094 Dt. 24.01.2024
TS Amount (lakhs) : 58.23 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
58.23
Resanction Cost :
58.23
Tentative Cost :
58.23
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
58.13
Demand :
57.78
Allotment :
26.79
Exp in CFY :
26.79
Total Up to Date Exp :
26.89
Construction Started
Sanction on : 11 months 23 hours ago
24 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 2 months 3 days from now
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर । -- as on 06-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: