Work Profile Report [51W1314]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E letter no 26103 लोक निर्माण अनुभाग 2
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
294.85
Resanction Cost :
294.85
Tentative Cost :
294.85
Exp. Upto Last Fy :
102.10
For CFY 2025-2026
Remaining :
192.75
Demand :
192.75
Allotment :
133.58
Exp in CFY :
133.58
Total Up to Date Exp :
235.68
Work completed
Sanction on : 9 months 9 hours ago
18 Oct 2024
Physical Progress:
At start of FY 2025-2026 :
13 %
Up to Date :
100 %
Tentative Completion date on : 2 weeks 4 days ago
30 Jun 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण दायित्व शेष -- as on 04-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: