Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 6.75 | 3.000 | 3.75 | 3.750 | 0.000 |
51W172 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 1377/।।।(2)/09-24(मा.मु.मं.घो.)/09 टी.सी.-1 दि. 23.3.2010
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 663.06 Lacs
Resanction Cost : 663.06 Lacs
Exp. Upto Last Fy : 475.92 Lacs
For CFY 2024-2025
Remaining : 187.14 Lacs
Demand : 187.15 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 475.92 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 65 %
Up to Date : 65 %
Sanction on :
14 years 1 month ago
23 Mar 2010
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 21: Final
Bottelneck: no issue
पहाड़ कटान का कार्य पूर्ण द्वितीय चरण का कार्य प्रगति पर -- as on 04-Apr-2024
Physical Peramenters