Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 7 | 7 | 0.000 | 7 | 4.000 | 0.000 |
51W2 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 299/लो0नि0-2/04-16(प्र्र्र्र्र्र्रा0आ0)/04 दिनांक 28.2.04
TS Amount (lakhs) : 97.3 Lacs
Financial Detail
Sanction Cost : 97.30 Lacs
Resanction Cost : 97.30 Lacs
Exp. Upto Last Fy : 13.98 Lacs
For CFY 2024-2025
Remaining : 83.32 Lacs
Demand : 83.32 Lacs
Allotment : 83.32 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 13.98 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
20 years 2 months ago
28 Feb 2004
Tentative Completion date:
10 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 20: Kattan
Bottelneck: no issue
छपान का कार्य पूर्ण ।वन निगम द्वारा वृक्षों के पातन की कार्यवाही प्रारंभ की गई है। स्वीकृत धनराशि में मात्र 4 किलोमीटर लंबाई में पहाड़ कटान कार्य हेतु अनुबंध गठित है जिसके सापेक्ष मार्ग के किलोमीटर 2 जो की नाप भूमि में है में पहाड़ कटान का कार्य प्रगति में है शेष कार्य हेतु पुनरीक्षित आगणन गठित कर स्वीकृति हेतु शासन को प्रेषित किया जाएगा -- as on 04-Apr-2024
Physical Peramenters