Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 0.500 | 0.65 | 0.000 | 0.000 |
No of Bridges | 5 | 5 | 5 | 0 | 0 | 0 |
51W201 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6691(1)/।।।(2)/10-18 ( प्रा.आ.)/2010 टी0सी0-6 दि0 31.12.2010
TS Amount (lakhs) : 73.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
73.91
Resanction Cost :
73.91
Tentative Cost :
73.91
Exp. Upto Last Fy : 34.66
For CFY 2024-2025
Remaining : 39.25
Demand : 39.25
Allotment : 14.00
Exp in CFY : 0.30
Total Up to Date Exp : 34.96
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
13 years 6 months ago
31 Dec 2010
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
1 year 3 months ago
31 Mar 2023
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 08-Apr-2024