Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 8.000 | 0 | 0.000 | 0.000 |
51W788 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा.सं. 751/111(2)/09-15 (एम0एल0ए0)/08 दिनांक 27.02.2009
TS Amount (lakhs) : 280 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
280.00
Resanction Cost :
436.86
Tentative Cost :
436.86
Exp. Upto Last Fy : 428.83
For CFY 2024-2025
Remaining : 8.03
Demand : 8.03
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 428.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
15 years 4 months ago
27 Feb 2009
Tentative Completion date:
1 year 2 months ago
30 Apr 2023
Actual Completion Date:
1 year 4 months ago
28 Feb 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 06-Nov-2023
Physical Peramenters