Work Profile Report [51W788]

मोलधार से सेरकी सिल्ला तक मार्ग का नवनिर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा.सं. 751/111(2)/09-15 (एम0एल0ए0)/08 दिनांक 27.02.2009

TS Amount (lakhs) : 280 Lacs

Budget Financial Head : SCSP ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

280.00

Resanction Cost :

436.86

Tentative Cost :

436.86

Exp. Upto Last Fy :

428.83

For CFY 2024-2025

Remaining :

8.03

Demand :

8.03

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

428.83

Work completed

Sanction on : 15 years 8 months ago

27 Feb 2009

Physical Progress:

At start of FY 2024-2025 :

100 %

Up to Date :

100 %

Tentative Completion date on : 1 year 6 months ago

30 Apr 2023

Actual Completion Date : 1 year 8 months ago

28 Feb 2023

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
8
8
8.000
0
0.000
0.000

Remark

view all

कार्य पूर्ण। -- as on 06-Nov-2023

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: