Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.15 | 1.15 | 1.150 | 0 | 0.000 | 0.000 |
51W998 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश संख्या - 2299/।।।(2)/19-20 (एम.एल.ए.)/2017 टी.सी. दि. 25.6.19
TS Amount (lakhs) : 460.43 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
460.43
Resanction Cost :
460.43
Tentative Cost :
460.43
Exp. Upto Last Fy : 441.11
For CFY 2024-2025
Remaining : 19.32
Demand : 19.32
Allotment : 2.80
Exp in CFY : 17.45
Total Up to Date Exp : 458.56
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
5 years 3 weeks ago
25 Jun 2019
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
3 months 2 weeks ago
30 Mar 2024
Remark
Bottelneck: no issue
कार्य पूर्ण -- as on 08-Nov-2023
Physical Peramenters