Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 0.000 | 0.000 |
52W169 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासनादेश सं0-6668/111(2)13-37(प्रा0आ0)/ 2013 दिनांक 26.11.2013
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
74.30
Resanction Cost :
74.30
Tentative Cost :
74.30
Exp. Upto Last Fy : 2.04
For CFY 2024-2025
Remaining : 72.26
Demand : 5.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
10 years 7 months ago
26 Nov 2013
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
मुआवजा वितरण हेतु पत्रावली गठन का कार्य गतिमान है। -- as on 12-Jul-2024
Physical Peramenters