Work Profile Report [52W169]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासनादेश सं0-6668/111(2)13-37(प्रा0आ0)/ 2013 दिनांक 26.11.2013
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : TSP ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
74.30
Resanction Cost :
74.30
Tentative Cost :
74.30
Exp. Upto Last Fy :
2.04
For CFY 2025-2026
Remaining :
72.26
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.04
none
Sanction on : 11 years 7 months ago
26 Nov 2013
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 days ago
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
ग्रामीणों द्वारा पुनः समरेखण विवाद। -- as on 03-Mar-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: