Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 8 | 8 | 0.000 | 8 | 0.000 | 0.000 |
52W193 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-5690/111(2)/14-06 (प्रा0आ0)/2014 दिनांक 15.10.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 65.76 Lacs
Resanction Cost : 65.76 Lacs
Exp. Upto Last Fy : 61.04 Lacs
For CFY 2024-2025
Remaining : 4.72 Lacs
Demand : 1.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 61.04 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
9 years 7 months ago
15 Oct 2014
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण, द्वितीय चरण का कार्य माह 03/2023 में पूर्ण किया जा चुका है। प्रथम चरण में भूमि दबान का मुआवजा कुछ कास्तकारों को कर दिया गया हैंै तथा कुछ कास्कारों द्वारा दस्तावेज उपलब्ध न होने के कारण मुआवजा वितरण नही किया जा सका। -- as on 09-Nov-2023
Physical Peramenters