Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
52W194 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-5690/111(2)/14-06(प्रा0आ0)/ 2014 दिनांक 15.10.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 49.32 Lacs
Resanction Cost : 49.32 Lacs
Exp. Upto Last Fy : 0.72 Lacs
For CFY 2024-2025
Remaining : 48.60 Lacs
Demand : 2.50 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.72 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 years 7 months ago
15 Oct 2014
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण। द्वितीय चरण की डी.पी.आर.नवीनतम दरों पर गठित कर 31 मार्च 2024 तक प्रेेषित कर दी जायेगी। -- as on 08-Mar-2024
Physical Peramenters