Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
52W232 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-3317/।।।(2)14-06(प्रा0आ0)/2014 दिनांक 26.05.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.32
Resanction Cost :
49.32
Tentative Cost :
49.32
Exp. Upto Last Fy : 2.76
For CFY 2024-2025
Remaining : 46.56
Demand : 2.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 2.76
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 5 %
Sanction on :
10 years 1 month ago
26 May 2014
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य पूर्ण, मुआवजा वितरण हेतु पत्रावली गठन की कार्यवाही गतिमान है। -- as on 12-Jul-2024
Physical Peramenters