Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
52W235 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-3317/।।।(2)/14-06 (प्रा0आ0)/2014 दिनांक 26.05.2014
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.66
Resanction Cost :
24.66
Tentative Cost :
24.66
Exp. Upto Last Fy : 0.04
For CFY 2024-2025
Remaining : 24.62
Demand : 1.00
Allotment : 0.30
Exp in CFY : 0.00
Total Up to Date Exp : 0.04
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 2 %
Sanction on :
10 years 1 month ago
26 May 2014
Tentative Completion date:
2 years 3 months ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
डी0पी0आर0 दिनांक 03.10.2022 की नवीनतम शेडयूल दरों पर गठित कर इस कार्यालय के पत्र 30 /1सी0 06.04 2023 को अधीक्षण अभियंता नवम वृत्त लो 0नि0वि0 देहरादून को प्रेषित| मुख्य अभियन्ता क्षे0का0 लो0नि0वि0,देहरादून के पत्रांक सं0-2572/09(105) याता0-स्तर-।, (क्षें0का0)/2023 दिनांक 17.05.2023 द्वारा आगणन आपत्तियों,में वापस, पुनः आपत्तियों का निराकरण कर इस कार्यालय के पत्र सं0-896/1सी0 दिनांक 25.08.2023 द्वारा रू0 81.79 लाख का आगणन अधी0अभि0,नवम् वृत्त,लो.नि.वि. देहरादून को प्रेषित। वृत्तीय कार्यालय द्वाराआगणन पुनः आत्तियों में वापस लौटाया गया है। विभाग द्वारा आपत्तियों का निराकरण कर संयुक्त निरीक्षण हेतु 14.03.2024 की तिथि निर्धारत की गई थी। संयुक्त निरीक्षण किया जा चुका है निरीक्षण आख्या अप्राप्त है। -- as on 14-Jul-2024
Physical Peramenters