Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
52W26 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005
TS Amount (lakhs) : 90.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
41.70
Resanction Cost :
90.53
Tentative Cost :
90.53
Exp. Upto Last Fy : 88.33
For CFY 2024-2025
Remaining : 2.20
Demand : 2.20
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 88.33
Technical sanction done
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 8 months ago
10 Nov 2005
Tentative Completion date:
1 year 1 month ago
31 May 2023
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 18: Final Approval
Bottelneck: no issue
पहाड़ कटान का कार्य 3.00 कि0मी0 माह 05 /2023 को पूर्ण ,दायित्व का भुगतान शेष | -- as on 02-Jun-2023
Physical Peramenters