त्यूनी-चकराता मो0 मार्ग से भंगार सम्पर्क मार्ग का विस्तार


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0-2658/111-2/06-17 (प्रा0आ0)/06 दि0 25.09.2006

TS Amount (lakhs) : 64.8 Lacs

Financial Detail (in Rs Lakhs)

Sanction Cost :

64.80

Resanction Cost :

64.80

Tentative Cost :

64.80

Exp. Upto Last Fy : 63.71

For CFY 2024-2025

Remaining : 1.09

Demand : 1.14

Allotment : 0.00

Exp in CFY : 0.00

Total Up to Date Exp : 63.71

Work completed

Physical Progress:

At start of FY 2024-2025 : 100 %

Up to Date : 100 %

Sanction on :
17 years 9 months ago
25 Sep 2006


Tentative Completion date:
3 years 2 weeks ago
30 Jun 2021


Actual Completion Date:
Not Yet Reported


Rating : 100

Remark

Bottelneck: no issue


माह 0 3/2023 कार्य पूर्ण|दायित्वों का भुगतान अवशेष है| -- as on 23-Apr-2023

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 4 2 2 0
Currently only Bank Gaurantee information is avilable