Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 13 | 13 | 13.000 | 0 | 0.000 | 0.000 |
No of Bridges | 1 | 1 | 1 | 0 | 0 | 0 |
Span of Bridges [m] | 20 | 24 | 24.000 | 0 | 0.000 | 0.000 |
52W34 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1754/111-2/5-64 (प्रा0आ0)/05 दि0 10.11.2005
TS Amount (lakhs) : 198.7 Lacs
Financial Detail
Sanction Cost : 198.70 Lacs
Resanction Cost : 562.53 Lacs
Exp. Upto Last Fy : 244.62 Lacs
For CFY 2024-2025
Remaining : 317.91 Lacs
Demand : 295.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 244.62 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
18 years 6 months ago
10 Nov 2005
Tentative Completion date:
1 year 11 months ago
09 Jun 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue