Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.5 | 4.5 | 4.5 | 0 |
Closed Work 52W373 :
Administrative Approval Detail : शासनादेश सं0-250/।।।(2)/20-30(प्रा0आ0)/2017, दिनांक 13.01.2020
TS Amount (lakhs) : 348.36 Lacs
Financial Detail
Sanction Cost : 348.36 Lacs
Resanction Cost : 348.36 Lacs
Exp. Upto Last Fy : 271.58 Lacs
For CFY 2024-2025
Remaining : 76.78 Lacs
Demand : 0.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 271.58 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
4 years 5 months ago
13 Jan 2020
Tentative Completion date:
3 years 1 month ago
29 May 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
माह 03/2021 में कार्य पूर्ण | -- as on 03-Mar-2023
Physical Peramenters